Ground floor – Guest room 1

Renovation of an individually rented ground-floor room with access to shared floor facilities: bathroom, kitchen and dining room.

Guest roomRenovation period : Janvier 2026 – Mai 2026Completed
FileAvailabilityRenovationPhotos

Information

Key information about the property and its renovation period.

AddressRue de la Bleich
68000 Colmar
France
TypeGuest room
Renovation periodJanvier 2026 – Mai 2026

Availability and contact

Occupied dates are greyed out. For pricing or special requests, direct contact is preferred.

Summary of renovation steps

This block will later be editable from the admin interface.

Read summary

Renovation summary

The project concerns an individually rented ground-floor room. The room is private, with access to shared floor facilities: bathroom, kitchen and dining room. The work was carried out from January to May 2026.

Room

  • Removal of the old bathroom located inside the room.
  • Decommissioning of former water and drainage connections.
  • Decommissioning of the former gas inlet by the utility provider.
  • Ordering and installation of a new window meeting more modern standards.
  • Installation of rails, plasterboard, plaster finishing and painting.
  • Spray insulation carried out by a specialist company.
  • New electrical installation with circuits dedicated to the floor.
  • Installation of a network connection for LAN and Wi-Fi repeater.
  • Installation of an air-to-air trisplit heat pump for the whole floor.
  • Floor work: levelling, insulation and laminate flooring.
  • Furnishing of the room.

Shared floor areas

  • Creation of a shared bathroom with shower, wall-hung toilet, washbasin and VMC.
  • Tiling work.
  • Installation of a reused and restored kitchen.
  • Replacement of old single-glazed windows with double glazing.
  • Spray insulation carried out by a specialist company.
  • Complete renewal of water supply lines using PER and copper.
  • Installation of an air-to-air trisplit heat pump.
  • Removal of the old gas heating system.
  • New dedicated electrical installation for the floor with a new distribution panel.
  • Rails, plasterboard, suspended ceilings, plaster finishing and painting across the different areas.
  • Joinery repairs and adjustments.
  • Suspended ceilings to improve acoustic insulation.
  • Creation of an access to the garage through the existing wall, including door installation.
  • Démolition
  • Électricité
  • Plomberie
  • Placo
  • Enduit
  • Peinture
  • Sols
  • Salle de bain

Photo documentation

Each series corresponds to a perspective. Titles can later be renamed in the editor.